12 teams · 44 students · April 8 – May 5, 2026
Sprint period: April 8 – May 5, 2026 (4 weeks) ·
Data sourced from GitHub Project boards via gh CLI
| # | Team | Repo | Members | Tasks | Est. Hours | Actual Hours | Notes |
|---|---|---|---|---|---|---|---|
| 1 | FlashFood | oierreguero/ProjectSE |
4 | 15 | 34.0 | 56.75 | Maddi led with 32.5h actual (+124% over estimate) |
| 2 | French Monsters | GeneralLMTV/Banking |
3 | 12 | 10.0 | 12.5 | Low total hours; elite768 returned with 3h after zero in Sprint 2 |
| 3 | INTAKE best | alexordazz/INTAKE |
4 | 15 | 36.5 | 39.5 | 🏆 Most balanced workload; only +8% deviation from estimates |
| 4 | JavaIsForMinecraft | Ekain001/sherlocktones |
3 | 24 | 53.5 | 46.05 | Well balanced; 2 optional tasks left Todo (4h est, 0h act) |
| 5 | JustAskClaude review | ha-haizea/ClaudeGenerateARepoName |
4 | 23 | 0.0 | ⚠️ No estimates entered; actual hours appear inflated (LMThen 215.8h) | |
| 6 | K (Fitly) | izeiaameztoi/Fitly |
3 | 22 | 54.7 | 46.5 | All 3 members active; Izeia (18.7h), Irati (17.2h), Kattalin (10.7h) |
| 7 | The Expats | tjarkberding/unipair |
4 | 23 | 32.6 | 35.3 | Well balanced; 15/17 tasks Done; Tjark led (15.3h) |
| 8 | WelcomeToTheJungle | demogice/osu-Toolkit |
3 | 23 | 116.0 | 57.25 | High estimates from 3 large shared tasks; 3 tasks still Todo (35h est) |
| 9 | dyansTeam | Nerea-z/dyansTeamProject |
3 | 40 | 48.25 | 66.75 | ✅ All tasks Done; most balanced team (all 3 within 5.5h of each other) |
| 10 | insert_group_name | oihan-ehu/insert_repo_name |
4 | 30 | 29.4 | 37.35 | Oihan led (13.6h); 3 items left in Backlog |
| 11 | lezoKapitalFumarong | Borobil21/LezoProject |
4 | 13 | 26.5 | 32.5 | All tasks Done; well-balanced across all 4 members |
| 12 | sassy_barbie_fishgif | bp-001/sassy-fish-project |
4 | 34 | 25.1 | 33.45 | Naiara led (12h); 2 Todo remaining; all 4 members active |
| TOTALS | 274 | 466.6 | 814.5 | Across 12 teams · 44 students | |||